[2024] Cumulative installed capacity of Wind Power in Japan :5,840.4MW (2,720 units)

2025/02/18

  • Reports

[2024] Cumulative installed capacity of Wind Power in Japan:
5,840.4MW (2,720 units)


*Figures may change due to confirmation of construction and decommissioning dates, etc.

 

2024

Cumulative capacity=5,840.4MW、2,720 units

Annual installation (Gross)=23 windfarms,  703.3MW, 170 units
Annual installation(Net) = 15 windfarms, 663.0MW, 120 units
Annual removes = 8 windfarms, 40.3MW, 50 units

*Gross : Pure installation Net : Installation considering removed windfarms


The Japan Wind Power Association (JWPA) has compiled preliminary figures on wind power generation installations in Japan as of the end of December 2024. The gross amount of new installations in 2024 was 703.3 MW (170 units) at 23 windfarms nationwide.
Meanwhile, net installed capacity excluding removed windfarms was 663.0 MW (120 units) at 15 windfarms, resulting in a cumulative installed capacity of 5,840.4 MW (2,720 units).

In offshore wind power in particular, the Ishikari Bay New Port Offshore Wind Farm has started operation, contributing to an increase in the amount of installed capacity as a new large-scale project. This will further expand Japan’s offshore wind power market, following the Akita Port Offshore Wind Farm and the Nyuzen Offshore Wind Power Farm, which went into operation in 2023.

By region, the Hokkaido region increased its installed capacity by approximately 455 MW compared to the previous year, ranking first in Japan. Furthermore, the capacity of single wind turbines continues to increase in size.

Note: Past performance figures may be revised at a later date due to discontinuation after publication of the figures or correction of the timing of start of operation, etc. Please refer to the links below for graphs of installed capacity by year since 2010, installed capacity by prefecture as of the end of December 2024, average output transition, and other data.

===>dounyuujisseki2024graph_EN

As of the end of December 2024, full-scale offshore wind power generation (those that cannot be directly accessed from land and require ships) is as follows.

Type Windfarm  Start of operation date Numbers of unit Capacity
Floating Sakiyama 2MW Floating Offshore Wind Turbine 4/2016 1 unit 2.0MW
Fixed Choshi Offshore Wind Power Plant 1/2019 1 unit 2.4MW
Floating Hibiki floating offshore Wind Turbine 5/2019 1 unit 3.0MW
Fixed Noshiro Port Offshore Wind Farm 12/2022 20 units 84.0MW
Fixed Akita Port Offshore Wind Farm 1/2023 13 units 54.6MW
Fixed Nyuzen Offshore Wind Power Farm 9/2023 3 units 7.5MW
Fixed Ishikari Bay New Port Offshore Wind Farm 1/2024 14 units 99.9MW
Total 7 windfarms 53 units 253.4MW

     

    pick up contents

    Cumulative installed capacity of wind power in 2023 Japan: 5,213.4 MW 2,626 Units
    JWPA Wind Vision 2023 -Contribution of wind power toward the realization of a safe, stable and sustainable society-
    Global Offshore Wind Summit - Japan 2024